Where;
Q = Order quantity
L = # of ply in a lay
G = # of garment in marker
C = # of cut per day
D = Available day for cutting
Assumption
- Factory has sufficient cutting table
 - Table length match the marker length
 - Equipment and labor available
 
- Cutting target > Sewing target
 - A 10% more cut is necessary for uninterrupted input
 - Cutting starts at least one day prior to starts bulk production
 - # of cut = # of marker
 
Example :
Item: Men’ Full Sleeve Shirt, Order Quantity: 24,000 pieces
Daily input to sewing section: 2,400 pieces, Available days for completion: 10
Calculate theoretical cut per day
Solution:
Q = 24,000 Pcs
L = 100
G = 12
D = 10
C = ?

A 10% more cut is necessary for uninterrupted input