Cutting plan mathematics

Some cut plan problem and solution  

Problem: 01
Make a cut plan based on the following information-
Maximum ply: 25
Maximum garments per marker: 3
Total qty: 225pcs

Size
L
M
L
XL
Qty
25
75
100
25

Solution:
Cut required= Total qty/ (Ply X Marker) = 225/(25 3) = 3

Cut No 1.
Ply=25, production=75

Size
S
M
XL
Qty
25
25
25

Cut No 2.
Ply=25, production=75

Size
L
M
L
Qty
25
25
25

Cut No 3.
Ply=25, production=75

Size
L
M
L
Qty
25
25
25

\ Total production=75+75+75=225 pcs.
   
Problem: 02
Make a cut plan based on the following information-
Maximum ply: 75
Maximum garments / marker: 4
Total qty: 1400pcs
  
Color
S
M
L
XL
RED
75
125
125
75
BLUE
150
150
150
150
YELLOW
75
125
125
75
TOTAL=
300
400
400
300

 Solution:
Cut required: Total qty/ (Ply X Marker) = 1400 / (75 X 4) = 4.6 » 5
  
Cut No 1.
Ply=75, production=300

Color
SIZE
S
M
L
XL
BLUE
QTY
75
75
75
75

 Cut No 2.
Ply=75, production=300

Color
SIZE
S
M
L
XL
BLUE
QTY
75
75
75
75

 Cut No 3.
Ply=75, production=300

Color
SIZE
S
M
L
XL
RED
QTY
75
75
75
75
  
Cut No 4.
Ply=75, production=300

Color
SIZE
S
M
L
XL
YELLOW
QTY
75
75
75
75

 Cut No 5.
Ply=50, production=200

Color
SIZE
M
M
L
L
RED
QTY
25
25
25
25
YELLOW
QTY
25
25
25
25

\ Total production=300+300+300+300+200=1400pcs

Problem: 03
Make a cut plan based on the following information-
Maximum ply: 42
Maximum garments / marker: 4
Total qty: 420pcs
  
Color
L
M
L
XL
RED
21
42
42
21
BLUE
42
42
42
42
YELLOW
21
42
42
21
TOTAL=
84
126
126
84

Solution:
Cut required: Total qty/ (Ply X Marker) = 420/ (42 X 4) =2.5 » 3

Cut No 1.
Ply=42, production=168

Color
SIZE
S
M
L
XL
BLUE
QTY
42
42
42
42

Cut No 2.
Ply=42, production=168

Color
SIZE
S
M
L
XL
RED
QTY
21
21
21
21
YELLOW
QTY
21
21
21
21

Cut No 3.
Ply=42, production=84

Color
SIZE
S
M
L
XL
RED
QTY

21
21

YELLOW
QTY

21
21


\ Total production= 168+168+84=420pcs